The resource cost of a project is calculated by multiplying the effort spent on each task with the billing code associated with the task. To associate a billing code with a task,
define a billing code as described here (if you already have billing codes defined, skip this step)
associate the billing code with the task in the schedule editing dialog (below). To do this,
double-click on the Billing code column of the resources table, and select the desired billing code from the drop-down list.
now the Estimated resource cost column will equal the effort times the rate of the billing code.